N.S. ConstructionVendor Evaluation Bee

Civil, structural, premium facade and finishing works

Past performance

Intake

Optional. Where the client already holds a record of how a bidder performed, this is how it gets in, as the spreadsheet it is kept in.

What a workbook has to carry

One sheet, one row per completed project, with a header row. These are the columns the scoring reads. Anything else in the file is left alone, and the project name, the contract value, the final cost, the milestones on time, the NCRs and the HSE incidents have to be there.

ProjectScopeContract value (INR)Final cost (INR)Variation claimsMilestones on time (%)Average delay (days)NCRsSnagsAverage snag closure (days)HSE incidentsLTIFRPermit compliance (%)Completed

Values can be written the way your team writes them: 742,00,00,000 and INR 742 crore are read the same way.

The vendors bidding on this RFI0 of 0 with an uploaded record
This step is optional.A vendor with nothing here is scored on its proposal alone, and the grid says so on the row.
Go to evaluation